By Reclamation's 2000 history, Hooker Dam on the upper Gila was deleted from the Central Arizona Project in December 1982, and on 18 June 2020 the Interstate Stream Commission voted to end the review of the diversion planned under the 2004 Arizona Water Settlements Act. The settlement money now pays for water projects in Catron, Grant, Hidalgo and Luna counties, and a bill to designate the Gila a wild and scenic river had passed neither chamber as of November 2026.
Hooker Dam on paper, 1930 to 1968
On 30 September 1968 Congress approved the Colorado River Basin Project Act, Public Law 90-537, which authorized the Central Arizona Project. Among its principal works the act listed "Hooker Dam and Reservoir or suitable alternative", a dam on the Gila River in New Mexico. It was to give effect to the act's New Mexico water provisions, in section 304(f). Reclamation had looked at the site long before. A state bibliography lists a 1930 Bureau of Reclamation report titled Hooker Dam Upper Gila River Investigations, Arizona - New Mexico. Reclamation's 2000 history of the project says the agency's 1947 plan included Hooker Dam, along with Buttes Dam in Arizona.
Sources: U.S. Congress, Public Law 90-537, Colorado River Basin Project Act (82 Stat. 885) (1968-09-30): Sec. 101 and closing line 'Approved September 30, 1968'; Sec. 301(a)(4), 82 Stat. 887; Jennifer E. Zuniga, Bureau of Reclamation, The Central Arizona Project (2000): Project Authorization, p. 21; New Mexico Office of the State Engineer / Interstate Stream Commission, Southwest New Mexico Bibliography: Hydrology catalog (Arizona Water Settlements Act studies) (n.d. (c. 2010s)): catalog entry 'Hooker Dam Upper Gila River Investigations' (also 'Upper Gila River Investigations of 1929-1930')
Section 304(f) told the Secretary of the Interior to offer New Mexico users contracts for an extra consumptive use of Gila water, meaning water used up rather than returned to the river. The ceiling was an annual average of 18,000 acre-feet over any ten consecutive years, reservoir evaporation included; an acre-foot covers an acre a foot deep. That use could begin only once Colorado River water reached downstream Gila users in Arizona in amounts that replaced what New Mexico took. Arizona contractors who used Gila water had to accept Colorado River water in exchange. A further 30,000 acre-feet a year waited on works to augment the Colorado River supply. All of it was junior, or second in line, to existing rights.
Hooker, Conner and Mangas, 1973 to 1990
Hooker's reservoir would have reached into proposed wilderness. In 1973 a Forest Service proposal for the Gila Wilderness said it would flood about 520 acres along the Gila and Turkey Creek, and that the dam had not been funded. In April 1977, by Reclamation's history, President Carter recommended deleting Orme, Hooker and Charleston dams from the project as too expensive. Congress agreed to drop their funding for 1978 but refused to deauthorize them. After further study Reclamation concluded that extreme western New Mexico had no real need for a storage reservoir and that Hooker's environmental impact was too damaging. In December 1982 Hooker Dam was deleted from the Central Arizona Project.1
Two other accounts date Hooker's end differently. The Gila Conservation Coalition's page on the river says Hooker failed in the 1970s because its reservoir would have drowned the wilderness. Richard Mahler's 2014 article on the coalition's 30th birthday, which the coalition reposted, says the project was abandoned by the mid-1980s. Reclamation's history ties its date to the deletion from the project.
Sources: The Gila River (Gila Conservation Coalition page) (2019): section 'Threats to the Gila River'; Richard Mahler (first in GetAGRIP, Spring 2014; reposted by Gila Conservation Coalition), Gila Conservation Coalition Marks Its 30th Birthday (2014-10-15): paragraph 4; Jennifer E. Zuniga, Bureau of Reclamation, The Central Arizona Project (2000): Construction History, p. 38
Dutch Salmon told Mahler how his opposition began. He recalled a fishing trip in September 1982 to the Gila east of the Mogollon Box, where he saw bighorn sheep, "exactly where the Hooker Dam was being proposed." In spring 1983, he said, he canoed down the Gila with his cat and dog, a trip that became his book Gila Descending and a slide show he took around the state. In 1984 he helped organize the Gila Conservation Coalition. It began, he said, as a counterweight to the Hooker Dam Association, a local group that backed a dam across the Gila a few miles upstream of its confluence with Mogollon Creek.
Hooker had a successor in Conner Dam. Mahler writes that public opposition, led in large part by the coalition, brought the withdrawal of the Conner proposal by late 1987. Salmon, appointed to the Interstate Stream Commission in 1985, attributed its death mainly to possible conflicts with endangered fish, a poor cost-benefit ratio and largely negative public reaction. A third proposal, a Mangas Creek diversion, was judged too costly for its benefits and dropped by Reclamation in 1990, the article says. The coalition's page puts the defeat of Conner Dam and the Mangas Diversion in the 1980s, over costs Silver City residents refused to pay. Asked who had pushed the dam schemes, Salmon named real estate interests, developers, bankers, the mining industry and chambers of commerce.
Sources: Richard Mahler (first in GetAGRIP, Spring 2014; reposted by Gila Conservation Coalition), Gila Conservation Coalition Marks Its 30th Birthday (2014-10-15); The Gila River (Gila Conservation Coalition page) (2019): section 'Threats to the Gila River'
Endangered fishes and a flycatcher, 1986 to 2013
Two fishes gained federal protection in 1986, when the Fish and Wildlife Service listed the spikedace and the loach minnow as threatened. Their critical habitat, stretches of stream formally designated for a listed species, went to court twice. Catron County sued over the first proposal in June 1993, and a federal district court in New Mexico set the habitat aside on 13 October 1994. The New Mexico Cattle Growers' Association and a coalition of counties sued over a 2000 designation of about 898 miles. On 31 August 2004 the court in New Mexico set it aside entirely. A replacement in March 2007 covered about 522.2 river miles, and on 23 February 2012 the Service moved both fishes to endangered.
Sources: U.S. Fish and Wildlife Service, Endangered and Threatened Wildlife and Plants; Endangered Status and Designations of Critical Habitat for Spikedace and Loach Minnow; Final Rule (77 FR 10810) (2012-02-23): 77 FR 10810, Background; 77 FR 10810, Summary and Dates; U.S. Court of Appeals for the Tenth Circuit, Catron County Board of Commissioners v. U.S. Fish & Wildlife Service, No. 94-2280, 75 F.3d 1429 (10th Cir. Feb. 2, 1996), as reproduced at 26 ELR 20808 (1996-02-02): Opinion, Background section (26 ELR 20808, para. beginning 'In 1985'); U.S. Fish and Wildlife Service, Endangered and Threatened Wildlife and Plants; Revocation of Critical Habitat for the Mexican Spotted Owl, Loach Minnow, and Spikedace, 63 FR 14378 (1998-03-25): 63 FR 14378-79, Supplementary Information, Background; U.S. Fish and Wildlife Service, Final Designation of Critical Habitat for the Spikedace and the Loach Minnow (65 FR 24328) (2000-04-25): 65 FR 24328, Summary; U.S. Fish and Wildlife Service, Designation of Critical Habitat for the Spikedace and the Loach Minnow; Final Rule (72 FR 13356) (2007-03-21): 72 FR 13358, Previous Federal Actions; 72 FR 13356, Summary
That 2012 rule said the Gila/Cliff Valley segment held more spikedace and loach minnow than any other area in their ranges. It said farming had at times dewatered the river there in the dry season. Citing a 2003 study by Soles, the Service said the valley's diversions, though modest, may remove the Gila's entire dry-season baseflow of about 40 cubic feet per second. A 2014 flow study by The Nature Conservancy and others said the two main diversions at the valley's upper end dry the river just below them. In 2007 the State Game Commission and The Nature Conservancy had bought 168 acres along more than a mile of the river there for $600,000 to protect the two fishes.2
Sources: U.S. Fish and Wildlife Service, Endangered and Threatened Wildlife and Plants; Endangered Status and Designations of Critical Habitat for Spikedace and Loach Minnow; Final Rule (77 FR 10810) (2012-02-23): 77 FR 10867; 77 FR 10812; see also response to comment 50, 77 FR 10880; David Gori, Martha S. Cooper, Kelly Kindscher and others (The Nature Conservancy et al.), Gila River Flow Needs Assessment (July 2014), chapter on riparian vegetation of the Cliff-Gila Valley (2014-07): riparian vegetation chapter, 'Young pioneer forests' section; New Mexico Department of Game and Fish, State Game Commission, Nature Conservancy purchase property on Gila River (news release, June 26, 2007) (2007-06-26): release, paragraph 1
On 27 February 1995 the Service listed the southwestern willow flycatcher as endangered. It cited habitat loss, a lack of adequate regulation and brood parasitism, in which cowbirds lay eggs in other birds' nests. Its 2013 critical habitat rule counted 262 territories at 8 upper Gila sites in 1999, 209 of them on a single ranch. At the U-Bar Ranch near Cliff, the Service wrote, many flycatchers nest in mature boxelders along irrigation ditches nearly 60 feet up, as they do nowhere else in their breeding range. It excluded the ranch, formerly owned by Phelps Dodge, because of a Freeport-McMoRan plan that provides, if necessary, for further conservation measures costing up to $500,000.
Sources: U.S. Fish and Wildlife Service, Final Rule Determining Endangered Status for the Southwestern Willow Flycatcher (60 FR 10694) (1995-02-27): 60 FR 10694, Summary; U.S. Fish and Wildlife Service, Designation of Critical Habitat for Southwestern Willow Flycatcher; Final Rule (78 FR 344) (2013-01-03): 78 FR 432; 78 FR 432, Freeport McMoRan U-Bar Ranch Management Plan
Fourteen thousand acre-feet, 2004 to 2014
Signed on 10 December 2004, the Arizona Water Settlements Act rewrote section 304(f). It let New Mexico consume up to an average of 14,000 acre-feet a year more from the Gila and its tributaries, in exchange for Central Arizona Project water for Arizona users downstream. It struck the contingent 30,000 acre-feet. New Mexico had until 31 December 2014 to tell the Interior Secretary whether it meant to build a New Mexico Unit to divert Gila water. The act provided $66 million in 2004 dollars for a New Mexico Unit Fund, in ten annual payments beginning in 2012, plus $34-62 million more toward building a unit if conditions were met.3, 4, 5
Sources: U.S. Congress, Public Law 108-451, Arizona Water Settlements Act (118 Stat. 3478) (2004-12-10): Sec. 212(d), 118 Stat. 3528; U.S. Congress, Public Law 90-537, Colorado River Basin Project Act (82 Stat. 885) (1968-09-30): Sec. 304(f)(2)
Money for a unit came with conditions. The fund could pay for the unit itself or for other water utilization alternatives in the Southwest Water Planning Region. For the extra construction money the act required a Record of Decision, the final federal approval after environmental review, in the Federal Register by 31 December 2019. It allowed the Secretary to extend that deadline for reasons outside New Mexico's control, but not beyond 31 December 2030. A commenter on the Fish and Wildlife Service's 2007 minnow rule warned that the 14,000 acre-feet would almost double adjudicated withdrawals from the Gila and San Francisco. Linda Stailey of the Gila valley acequias, the community ditches, told the New Mexico Acequia Association in 2017 that the Gila Basin Irrigation Commission had been organized in response to the act.
Sources: U.S. Congress, Public Law 108-451, Arizona Water Settlements Act (118 Stat. 3478) (2004-12-10): Sec. 212(i), 118 Stat. 3529; Sec. 212(j)(2), 118 Stat. 3530; U.S. Fish and Wildlife Service, Designation of Critical Habitat for the Spikedace and the Loach Minnow; Final Rule (72 FR 13356) (2007-03-21): 72 FR 13366, comment 51; New Mexico Acequia Association (interview with Linda Stailey of the Gila valley acequias), Community Spotlight: Acequias off the Gila River in South West NM (2017-09-25): interview, history answer
High Country News reported that on 24 November 2014 the commission voted, with one dissent, to build a diversion and storage project on the upper Gila. The approved proposal piped water across the Continental Divide to Deming, which the paper said "could lead to a 10-fold increase in municipal water rates". It reported that the act made up to $128 million in federal funds available for a diversion, or about half that for smaller water projects. By then, it said, the state had spent $7 million studying diversion plans.6, 7
The CAP Entity's diversion and its end, 2015 to 2021
A joint powers agreement effective 27 July 2015 created the New Mexico CAP Entity. Its members were the Interstate Stream Commission, four Gila irrigation associations, Catron, Grant, Luna and Hidalgo counties, Santa Clara, Deming, Lordsburg and two soil and water conservation districts. At Cliff-Gila three community ditches still diverted from the river: the Upper Gila, Fort West and Gila Farms. Reclamation's 2020 draft environmental impact statement said their irrigators hold senior rights established in the 1880s. In 2017 the CAP Entity, the diversion's proponent, told legislators its Phase I diversion would sit near the existing Upper Gila Diversion site. Its preliminary design, the entity said, would deliver up to 150 cubic feet per second to both the east and west irrigation systems.
Sources: Gabriel Ramos and John Arthur Smith (sponsors), Senate Bill 243 (54th Legislature, 2nd Session, 2020): New Mexico Central Arizona Project Entity Act: Sec. 2(D), p. 2 lines 5-15; U.S. Bureau of Reclamation and New Mexico Interstate Stream Commission (joint leads), New Mexico Unit of the Central Arizona Project, Draft Environmental Impact Statement, Volume 1 (2020-03-09): sec. 2.3, PDF p. 34; New Mexico CAP Entity (handout to the Legislature's Interim Water and Natural Resources Committee), Briefing for The Interim Water & Natural Resources Committee on the NM CAP Projects (Item 5, Background on AWSA) (2017-11-13): p. 4, 'Contemplated Projects'; New Mexico Interstate Stream Commission, NM Interstate Stream Commission: AWSA decisions and issues (Water and Natural Resources Committee handout, Aug. 6, 2020) (2020-08): slide 'NM Unit: NEPA Process and Roles'
New Mexico Political Report wrote in July 2019 that the plan included replacing and repairing ditches in the Cliff-Gila Valley and building storage ponds there. It also described a 155-foot concrete weir, a low dam that water spills over. Federal review had begun in June 2018 with Reclamation and the commission as joint leads. In June 2019 the commission decided to give no further funding beyond fiscal 2020 until it had reviewed the draft statement. In December 2019, the commission later told legislators, the Interior Secretary denied the CAP Entity's request to extend the deadline for the extra construction money. That decision permanently withheld $56.3 million in federal funding.8
Sources: Laura Paskus, New Mexico Political Report, Faced with costs, officials scale back Gila diversion plans (2019-07-08): article body; New Mexico Interstate Stream Commission, NM Interstate Stream Commission: AWSA decisions and issues (Water and Natural Resources Committee handout, Aug. 6, 2020) (2020-08)
Opponents attacked the yield and the cost. The Gila Conservation Coalition argued that Reclamation estimated the project would provide "an average of 2,600 acre-feet per year", with no water at all in many years. In 2019 the coalition said the commission and the CAP Entity had spent $15 million over 15 years without identifying a feasible diversion project.
Reclamation and the commission published the draft statement on 24 April 2020, and its comment period closed on 8 June with more than 500 comments. On 18 June 2020 the commission voted to end the environmental review and not to fund its completion. The Las Cruces Sun-News reported the vote as 7-2 and said it effectively ended the project. The coalition, reporting the same count, urged that about $70 million in remaining settlement funds go to projects such as the Grant County Regional Water Supply Project.8, 9
Sources: New Mexico Interstate Stream Commission, NM Interstate Stream Commission: AWSA decisions and issues (Water and Natural Resources Committee handout, Aug. 6, 2020) (2020-08): slide 'NEPA Process: Timeline of Main Events', June 8, 2020; Bureau of Reclamation, Termination of Notice of Intent To Prepare an Environmental Impact Statement, New Mexico Unit of the Central Arizona Project; Catron, Grant, and Hidalgo Counties (86 FR 21763) (2021-04-23): Supplementary Information; Las Cruces Sun-News; reposted by New Mexico Wilderness Alliance, New Mexico Gila River diversion project nixed by Interstate Streams Commission (Las Cruces Sun-News, reposted by New Mexico Wild) (2020-06-19): paras. 1-2
On 7 July 2020 the CAP Entity voted to reject ending its 2016 funding agreement by mutual consent and to pursue dispute resolution. Reclamation's notice gives 15 October 2020 as the date the funding agreement was terminated, and Reclamation formally ended work on the statement on 23 April 2021. The commission stressed that its June votes did not change New Mexico's entitlement to up to 14,000 acre-feet of settlement water.10, 11
Sources: New Mexico Interstate Stream Commission, NM Interstate Stream Commission: AWSA decisions and issues (Water and Natural Resources Committee handout, Aug. 6, 2020) (2020-08): slides 'Subsequent Events' and 'Next Steps to Wind Down the NEPA Process'; slide 'Interstate Commission's Actions in June 2020'; Bureau of Reclamation, Termination of Notice of Intent to Prepare an Environmental Impact Statement, New Mexico Unit of the Central Arizona Project (FR Doc. 2021-08511) (2021-04-23): Supplementary information
Where the settlement money went, 2016 to 2026
Part of the fund had gone to other work before the vote. From 2014 to 2016 the commission allocated $9.1 million to 16 water projects outside the New Mexico Unit in the four-county region. The largest listed grant, $2,100,000, went to the Town of Hurley Water Supply Project, Phase 1, whose construction the commission said in 2020 was effectively on pause because of water quantity problems and arsenic. Another $1,250,000 was allocated to the Gila Basin Irrigation Commission for Phase I of a plan to replace three earthen push-up dams in the Cliff-Gila Valley with more permanent structures, starting with the Upper Gila Ditch dam. By July 2020 its design was complete. By mid-2022 eight of the 16 projects were complete, seven were on hold, being reassessed or ended, and one was ongoing.
Sources: New Mexico Interstate Stream Commission, NM Interstate Stream Commission: AWSA decisions and issues (Water and Natural Resources Committee handout, Aug. 6, 2020) (2020-08); Rolf Schmidt-Petersen, Director, Interstate Stream Commission, New Mexico Unit Fund (Water and Natural Resources Committee presentation) (2022-07-26): slide 3, 'Status of Non-NM Unit Projects'
All ten federal payments were deposited between January 2012 and January 2021, and in July 2022 the commission's director, Rolf Schmidt-Petersen, reported the fund at $85.6 million. Under New Mexico's 2021 Unit Fund Act it pays for water projects in Catron, Grant, Hidalgo and Luna counties. In August 2026 the commission described a pilot cycle of 11 planning and design projects worth $4.3 million, with a second $26 million cycle taking applications. One example was Cliff-Gila River Stabilization, three in-stream structures to protect irrigation works, at a total cost of $7,770,095.81 and a fund share of $737,313.45. Another was design to rehabilitate a Bayard well and transmission line for Santa Clara and Silver City, part of the Grant County Regional Water Project.
Sources: Rolf Schmidt-Petersen, Director, Interstate Stream Commission, New Mexico Unit Fund (Water and Natural Resources Committee presentation) (2022-07-26): slide 2, 'NM Unit Fund Status'; Jesse Shapiro, AWSA Manager, Interstate Stream Commission, Update on the NM Unit Fund (Water and Natural Resources Committee, August 31, 2026) (2026-08-31): slides 2-3; slides 3 and 6; slide 'Example Project: Cliff-Gila River Stabilization'; slide 'Example Project: Bayard Well Design'
A wild and scenic bill, 1992 to 2026
In 1992 the Bureau of Land Management's Mimbres resource management plan proposed the Gila Lower Box, 2,480 acres, and the Gila Middle Box, 760 acres, as Wild and Scenic River study areas. At a Senate hearing on 7 June 2022 on an earlier bill, S. 3129, the bureau said that bill would designate all but 0.84 mile of the river within the Lower Box. It asked the sponsors to include the remainder. Senator Martin Heinrich's office put out an account of the hearing. In it, the Forest Service witness, Chris French, answered that the bill would affect neither water rights nor nearby private landowners' rights.12
Sources: U.S. Senate Committee on Energy and Natural Resources, Senate Report 118-67, M.H. Dutch Salmon Greater Gila Wild and Scenic River Act (to accompany S. 776) (2023-07-19): Statement of Nada Wolff Culver, BLM, reprinted in the report; Office of Sen. Martin Heinrich, Heinrich Bill To Designate Gila River As Wild & Scenic Gains Momentum In Key Hearing (press release) (2022-06-07): paragraph 4
On 10 April 2025 Senators Martin Heinrich and Ben Ray Luján introduced S. 1476, the M.H. Dutch Salmon Greater Gila Wild and Scenic River Act. Rep. Gabe Vasquez introduced the House companion, H.R. 2903, the same day. The bill's longest main-stem piece is a segment of about 34.9 miles of the Gila, to be classed as wild. It would withdraw federal land in designated segments from mining claims and from mineral and geothermal leasing, subject to valid existing rights. Without the holder's consent it would not abrogate existing rights, among them grazing permits, water rights, points of diversion and water infrastructure. It says it does not amend or affect the Arizona Water Settlements Act.
Sources: Sen. Martin Heinrich (for himself and Sen. Ben Ray Luján), S. 1476 (119th Congress), M.H. Dutch Salmon Greater Gila Wild and Scenic River Act, as introduced (2025-04-10): Sec. 1; header 'April 10, 2025'; Sec. 2(b), new para. (233)(E)(i); Sec. 2(c); Sec. 2(g)(1) and (g)(4); Library of Congress / GPO, Bill status XML, H.R. 2903 (119th Congress) (2025): actions, 2025-04-10; sponsor and cosponsor fields
Two agencies opposed the bill at a Senate subcommittee hearing on 2 December 2025. Christopher French, associate chief of the Forest Service, said USDA did not support the designations, calling them contrary to the Administration's commitment to "energy dominance and economic growth." He testified that 25 segments in the bill crossing the Gila National Forest had not been found eligible in the plan revision begun in 2015. Jon Raby of the Bureau of Land Management said the Interior Department did not support expanding designations "during the national energy emergency". He described the bill as covering nearly 450 miles of rivers and creeks.
Sources: Christopher French, USDA Forest Service, Statement of Christopher French, Associate Chief, USDA Forest Service, Senate ENR Subcommittee on Public Lands, Forests and Mining (incl. S. 1476) (2025-12-02): p. 9, S. 1476 section; p. 9; Jon Raby, BLM, U.S. Department of the Interior, Statement of Jon Raby, Nevada State Director, Bureau of Land Management, Senate ENR Subcommittee legislative hearing (incl. S. 1476) (2025-12-02): pp. 17-18 of 19 (S. 1476 summary and 'Analysis')
Two documents give different Lower Box mileages. A 2023 Senate committee report on S. 776, an earlier version of the Greater Gila bill, listed about 6.1 miles of the Lower Box as wild and 3.1 miles as recreational. The bureau's 2025 testimony on S. 1476 gave 6.1 miles wild and 2.1 miles recreational in the Lower Box, and 2.4 miles of the Middle Box as wild.
Sources: U.S. Senate Committee on Energy and Natural Resources, Senate Report 118-67, M.H. Dutch Salmon Greater Gila Wild and Scenic River Act (to accompany S. 776) (2023-07-19): Changes in Existing Law: Wild and Scenic Rivers Act sec. 3(a)(231)(G) 'Gila river, lower box' and (H) 'Gila river, middle box'; Jon Raby, BLM, U.S. Department of the Interior, Statement of Jon Raby, Nevada State Director, Bureau of Land Management, Senate ENR Subcommittee legislative hearing (incl. S. 1476) (2025-12-02): p. 17 of 19, S. 1476 section, para. 1
As of November 2026 that December hearing was the last action on S. 1476, and neither chamber had passed the bill. On the river, the Gila National Forest prohibits gas motors and says "Some non-motorized watercraft may operate on the Gila River". Its Mogollon Box Day Use Area sits at the confluence of the Gila and Mogollon Creek, at 4,639 feet, for fishing, non-motorized boating and picnicking. Salmon placed the Hooker Dam Association's dam a few miles upstream of that confluence. On 23 October 2026 the Forest Service reported that high Gila flows had overtopped the banks into the day use area, and its vehicle gate was locked.
Sources: Library of Congress / GPO, Bill status XML, S. 1476 (119th Congress) (2025-12): actions list, 2025-12-02; USDA Forest Service, Gila National Forest, Gila National Forest: Water Activities (2026-05-20): section 'Boating - Non-Motorized'; USDA Forest Service, Gila National Forest, Gila National Forest: Mogollon Box Day Use Area (2026-10-23): Current Conditions; General Information; Richard Mahler (first in GetAGRIP, Spring 2014; reposted by Gila Conservation Coalition), Gila Conservation Coalition Marks Its 30th Birthday (2014-10-15): paragraph 3
Part 5 of 7 of the series The Gila River in New Mexico: forks, valley and water.
Sources
- The 1973 proposal noted that a reservoir behind the planned Hooker Dam on the Gila (Central Arizona Project) would flood about 520 acres of the proposed wilderness along the Gila and Turkey Creek; the dam had not been funded. A Proposal, Gila Wilderness, Gila National Forest, New Mexico, Forest Service, A Proposal, Gila Wilderness (1973), archive.org CAT87879644 djvu text, Environmental impact section. View source ↗ (documented)
- In 2007 the State Game Commission and The Nature Conservancy bought 168 acres along more than a mile of the Gila River in the Cliff-Gila valley for $600,000 to protect spikedace and loach minnow habitat. State Game Commission, Nature Conservancy purchase property on Gila River (news release, June 26, 2007), NMDGF press release, June 26, 2007, paras. 1-2 and 4. View source ↗ (documented)
- The Arizona Water Settlements Act, signed December 10, 2004, let New Mexico consume up to an average of 14,000 acre-feet a year more from the Gila River and its tributaries, in exchange for Central Arizona Project water delivered to downstream Arizona users. Arizona Water Settlements Act, Public Law 108-451, 118 Stat. 3478 (Dec. 10, 2004), Pub. L. 108-451 sec. 212(d), amending 43 U.S.C. 1524(f)(1); 118 Stat. 3528. View source ↗ (documented)
- The act required New Mexico to tell the Secretary of the Interior by December 31, 2014, whether it intended to build a 'New Mexico Unit' to divert Gila water. Arizona Water Settlements Act, Public Law 108-451, 118 Stat. 3478 (Dec. 10, 2004), sec. 212(c), 118 Stat. 3527. View source ↗ (documented)
- The act provided $66 million (2004 dollars) for a New Mexico Unit Fund in ten annual payments beginning in 2012, plus $34-62 million more toward building a New Mexico Unit if conditions were met. Arizona Water Settlements Act, Public Law 108-451, 118 Stat. 3478 (Dec. 10, 2004), sec. 107(a), new sec. 403(f)(2)(D)(i)-(ii), 118 Stat. 3494-95. View source ↗ (documented)
- High Country News reported that on November 24, 2014, the Interstate Stream Commission voted, with one dissent, to build a diversion and storage project on the upper Gila, a decision it said marked the beginning of the end of a contentious ten-year planning process. New Mexico commission votes to divert Gila River, HCN, Sarah Tory, Nov. 25, 2014, paras. 1, 3. View source ↗ (reported)
- HCN reported that the act made up to $128 million in federal funds available for a diversion, or about half that for smaller water projects, and that the state had already spent $7 million studying diversion plans. New Mexico commission votes to divert Gila River, HCN, Nov. 25, 2014, para. 2. View source ↗ (reported)
- The Bureau of Reclamation and the Interstate Stream Commission published a draft environmental impact statement for the Gila diversion (New Mexico Unit) on April 24, 2020, after a notice of intent of June 12, 2018. Termination of Notice of Intent To Prepare an Environmental Impact Statement, New Mexico Unit of the Central Arizona Project; Catron, Grant, and Hidalgo Counties (86 FR 21763), 86 FR 21763 (Apr. 23, 2021), Summary. View source ↗ (documented)
- The Gila Conservation Coalition, which opposed the diversion, reported the June 2020 vote as 7-2 and urged that about $70 million in remaining settlement funds go to projects such as the Grant County Regional Water Supply Project. Breaking: ISC votes to end Gila diversion project, GCC press statement, para. 3. View source ↗ (reported)
- On June 18, 2020, the Interstate Stream Commission voted to stop the environmental review of the Gila diversion and not fund its completion; the funding agreement was terminated October 15, 2020. Termination of Notice of Intent To Prepare an Environmental Impact Statement, New Mexico Unit of the Central Arizona Project; Catron, Grant, and Hidalgo Counties (86 FR 21763), 86 FR 21763 (Apr. 23, 2021), Supplementary information. View source ↗ (documented)
- The Bureau of Reclamation formally ended preparation of the New Mexico Unit EIS, covering Catron, Grant and Hidalgo counties, by Federal Register notice on April 23, 2021. Termination of Notice of Intent To Prepare an Environmental Impact Statement, New Mexico Unit of the Central Arizona Project; Catron, Grant, and Hidalgo Counties (86 FR 21763), 86 FR 21763 (Apr. 23, 2021), Summary. View source ↗ (documented)
- BLM's 1992 Mimbres plan proposed the Gila Lower Box (2,480 acres) and Gila Middle Box (760 acres) as Wild and Scenic River study areas. Mimbres Resource Management Plan and Environmental Impact Statement: Final, Proposed Mimbres RMP / Final EIS, October 1992 (archive.org mimbresresourcem00unit), Ch. 2, The Proposed Plan, wilderness/WSR subsection. View source ↗ (documented)
"Documented" means the source is a record of the time or a direct survey; "reported" means a later account or secondary history, attributed in the text.
Cite this page: “Dams, a diversion and a wild river.” Grant County Atlas, Salars.net, first published 19 November 2026. https://atlas.salars.net/stories/gila-river/dams-a-diversion-and-a-wild-river
Discussion
What would you add or question? Comments are reviewed before they appear.
Loading comments…